Tuesday the 30th of june,we got instructions from Diederick that as from today we are goingto be in the workplace till friday i.e. there won't be any classes.("what a nice way to ease the assessment tension")
Maintenance Day
Today two groups was assigned a task to intall 10 spotlights around the garden area at the Guesthouse where as the other team were assigned a task to do maintenance around the farm checking all the burnt out globes, faulty connections and equipments.
We started the task with a bang as w digged a trench for the suffix cable at the guesthouse's main entrance faster than expected, then we installed 3 spotlights there.
Furthermore, as the day progressed, a problem was encounted at the gardens were we had to dig a trench from the inside of the garden were big trees roots and another suffix laying in the surface of the ground,then all the way through the area to the braai area.Because of those tree and grass roots and the suffix laying there in the ground, we had to slower our pace so that we won't damage anything.
However,as we carried on digging and laying(installing) the cable, another problem was encounted were the cable was now finished and short but at least we installed 3 more spotlights giving a total of 6 spotlights installed.Now the weird part of it was that all this happend before lunch time(12h30) as it usually took us more time.